Menu

Ida Street Box Culvert



Omaha, NE

E&A was hired to widen the existing box culvert over the drainage to the north branch of the West Papillion Creek in preparation for the four-lane Ida Street expansion.

Description

The wetland delineation area of investigation was located along Ida Street from the Papio-Missouri NRD Damsite 15A project, extending east for 2,500 feet to North 168th Street. The Ida Street Box Culvert required installation of 28 linear feet of double 5’ x 5’ pre-cast concrete box culvert that tied into the existing box culvert and associated rip rap and wing walls.

Key Partners

U.S. Army Corps of Engineers

Services Provided

Wetlands Services